2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for May 4–22
Below is the anticipated schedule of work from May 4 to 22, 2026.
Brighton High School
Technology Suite:
- Heat Pump warranty items
- Painting touch-ups
- Lighting Installation – CAD room
Door 20 Addition:
- Electrical work
- Door Hardware
Hallways & Pool Area:
- Drinking Fountain replacements
- Drywall work
- Painting
Music Suite:
- Electrical rough-in
- Mechanical rough-in – ductwork
- Insulation and Vapor Barrier
- Framing and Drywall
Athletic Fields and New Entry Lane:
- Currently at standstill, will continue work once soil management plan is set in place
Boiler Room/MDP:
- Mechanical & Plumbing Rough-In
- Electrical conduit rough-in and panel work
- Electrical & Plumbing Demo
- Electrical lighting rough-in
- Plumbing sump pump piping
Twelve Corners Middle School
STEAM Suite:
- Painting
- Electrical Work
Elevator:
- Camera Installation
- Electrical panel work & testing
- Inspections
French Road Elementary School
Main Lobby/Secure Vestibule:
- Door Hardware
- Painting touch-ups
Freezer/Cooler Addition:
- Electrical Disconnections
- CMU block wall
- Electrical rough-in
Council Rock Primary School
Crawlspace:
- Plumbing Lines for classroom sinks
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.