Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for November 9 to 20, 2026
Below is the anticipated schedule of work from November 9 to 20.
Brighton High School
Music Suite:
-
Punchlist work consisting of door adjustments, drywall work, lighting controls
Door 20 Addition:
-
Punchlist work consisting of Ceiling Work
Hallways:
-
Painting
-
Flooring Prep including grinding and moisture mitigation
-
Speaker Wiring
Rooms 154/156/Main Lobby/352/354/408
-
Electrical Rough-In
-
Foundation Work – Sampling Crusher for Proctor/Compaction
-
Framing
Athletic Fields and New Entry Lane:
-
Soil management plan is set in place. Working with DEC for work approvals.
-
Soil testing around the site for topsoil analysis – following DEC guidelines
-
Saw cutting asphalt & Excavation
-
Conduit Install & Light Pole Base Rough-In
-
Charging Station Work
Boiler Room/MDP:
-
Steel Work
-
Roofing
-
Cleaning
-
Concrete Infills
-
Controls Programming
Twelve Corners Middle School
Sitework:
-
Dumpster Fence & Posts Install
French Road Elementary School
Bus Loop/Parking Lot:
-
Signage Installation
-
Flag Pole Installation
Freezer/Cooler Addition:
-
Flooring
-
Electrical Finishes
-
Sump Pump Vent Piping
Dumpster Enclosure:
-
Fencing Work
Boiler Room:
-
Wall demolition
-
Electrical disconnections
Council Rock Primary School
-
Pre-Abatement Demo (Electrical) - Classrooms 26, 28, and 30
-
Abatement Demo - Classrooms 26, 28, and 30
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.