2025-26 Construction Schedule
Brighton Construction Schedule
Brighton Construction Schedule for April 13 – May 1
Below is the anticipated schedule of work from April 13 to May 1, 2026.
Brighton High School
Technology Suite:
- Shop equipment connections and adjustments
- Electrical finishes
Door 20 Addition:
- Electrical work
Hallways and Pool Area:
- Drinking Fountain replacements
- Drywall work
- Painting
Music Suite:
- Electrical rough-in
- Mechanical rough-in – piping and ductwork
- Framing and drywall
Athletic Fields and New Entry Lane:
- Currently paused, will continue work once soil management plan is set in place
Boiler Room/MDP:
- Mechanical and plumbing rough-in
- Electrical conduit rough-in and panel work
- Electrical and plumbing demo
- Plumbing sump pump piping
Twelve Corners Middle School
STEAM Suite:
- Painting
- Electrical Work
Elevator:
- Camera Installation
- Electrical panel work and testing
- Inspections
French Road Elementary School
Exterior Canopy:
- Roofing drainage work dependent on weather
Main Lobby/Secure Vestibule:
- Door Hardware
- Painting touch-ups
Freezer/Cooler Addition:
- Excavation
- Foundation work – pile driving
- Stoned laydown area
- Electrical Disconnections
- Plumbing drain line work
Council Rock Primary School
Crawlspace:
- Plumbing Lines
Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.
Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.