Skip to main content

Brighton Central School District

Every Child, Every Day, Every Way

2025-26 Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for May 4–22

Below is the anticipated schedule of work from May 4 to 22, 2026.

Brighton High School

Technology Suite:

  • Heat Pump warranty items
  • Painting touch-ups
  • Lighting Installation – CAD room

Door 20 Addition:

  • Electrical work
  • Door Hardware

Hallways & Pool Area:

  • Drinking Fountain replacements
  • Drywall work
  • Painting

Music Suite:

  • Electrical rough-in
  • Mechanical rough-in – ductwork
  • Insulation and Vapor Barrier
  • Framing and Drywall

Athletic Fields and New Entry Lane:

  • Currently at standstill, will continue work once soil management plan is set in place

Boiler Room/MDP:

  • Mechanical & Plumbing Rough-In
  • Electrical conduit rough-in and panel work
  • Electrical & Plumbing Demo
  • Electrical lighting rough-in
  • Plumbing sump pump piping

Twelve Corners Middle School

STEAM Suite:

  • Painting
  • Electrical Work

Elevator:

  • Camera Installation
  • Electrical panel work & testing
  • Inspections

French Road Elementary School

Main Lobby/Secure Vestibule:

  • Door Hardware
  • Painting touch-ups

Freezer/Cooler Addition:

  • Electrical Disconnections
  • CMU block wall
  • Electrical rough-in

 

Council Rock Primary School

Crawlspace:

  • Plumbing Lines for classroom sinks

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.

A construction schedule for 2025-26 lists projects for several schools, including Brighton and Twelve Corners.