2025-26 Construction Schedule

Brighton Construction Schedule

Brighton Construction Schedule for May 26 – June 12

Below is the anticipated schedule of work from May 26 to June 12, 2026

Brighton High School

Technology Suite:

  • Heat Pump warranty items
  • Ductwork adjustments
  • Painting touch-ups
  • Lighting Installation – CAD room

Door 20 Addition:

  • Punchlist work consisting of painting, floor base, and flooring.

Hallways & Pool Area:

  • Drinking Fountain replacements
  • Drywall work
  • Painting

Music Suite:

  • Electrical rough-in
  • Mechanical rough-in – ductwork
  • Insulation & Vapor Barrier
  • Framing & Drywall

Athletic Fields and New Entry Lane:

  • Currently at standstill, will continue work once soil management plan is set in place

Boiler Room/MDP:

  • Mechanical piping rough-in for boilers
  • Electrical wiring for boilers & pumps
  • Electrical lighting install, fire devices, and exit signs
  • Plumbing piping rough-in for boilers

Twelve Corners Middle School

STEAM Suite:

  • Painting
  • Electrical Work

Elevator:

  • Camera Installation
  • Inspections

French Road Elementary School

Main Lobby/Secure Vestibule:

  • Painting touch-ups

Freezer/Cooler Addition:

  • Exterior brick installation
  • Steel installation
  • Electrical rough-in
  • Plumbing rough-in

Council Rock Primary School

No work at this time

Please note that our schedules are always subject to change based on many factors and opportunities including manpower, material availability, and weather.

Brighton Central School District construction projects will follow the local Town of Brighton Construction Noise Ordinance Hours of 7 a.m. to 7 p.m. Monday through Friday. Please anticipate that there may be varying loud noise between those hours to allow for construction to advance.

A construction schedule for 2025-26 lists projects for several schools, including Brighton and Twelve Corners.